Maintenance

January 2025
Jan 01, 2025
1 maintenance

Additional London ISP

Maintenance

Resolved Jan 01 at 09:00pm EST

We wanted to inform you that we will be adding a new UK Internet Service Provider. While we expect this process to be seamless and without any interruptions to our network, we wanted to provide you with a heads-up just in case there are any unforeseen issues.

February 2025
Feb 27, 2025
1 maintenance

DAL-5-01 VPS Migration

Maintenance

Resolved Feb 27 at 02:57pm EST

Most VPS servers have completed migration and are back online. If your server is still offline, please access your VPS dashboard to manually start it.

1 previous update

Feb 24, 2025
1 maintenance

ASH-5-01 VPS Migrations

Maintenance

Resolved Feb 24 at 05:57pm EST

Migration is now completed. If your VPS is not online or booted, open a ticket.

4 previous updates

Feb 21, 2025
1 maintenance

Main Website: Reworking our docker containers

Maintenance

Resolved Feb 21 at 08:00pm EST

We’re reworking our dockers containers to better handle DDoS attacks.

All other critical websites are online and not affected.

You can use our billing portal for all important tasks:

https://billing.1of1servers.com/

Feb 17, 2025
1 maintenance

Network Upgrade: 40G Crossconnect Ashburn, VA

Maintenance

Resolved Feb 17 at 02:24pm EST

Thanks for your patience, we appreciate it! We are now upgraded to 40G!

9 previous updates

Feb 14, 2025
1 maintenance

ISP Addition in Dallas – Brief Connectivity Blip

Maintenance

Resolved Feb 14 at 01:00pm EST

We’re adding a new ISP in Dallas to help resolve the intermittent disconnect issues we’ve experienced. The expected downtime is approximately 30 seconds while the new routing takes effect, resulting in a brief network blip.

March 2025
Mar 13, 2025
2 maintenances

Dallas Datacenter Relocation - Group A

Maintenance

Resolved Mar 13 at 11:11am EDT

At this time all Group A migrations have been completed. If you are still seeing your server offline, please log into your client portal and navigate to your server's control panel and boot from there.

If after this you find any issues, please open a ticket from your client portal.

This portion of the maintenance has been marked Resolved at this time.
Thank you for your patience.

10 previous updates

Dallas Datacenter Relocation - Group B

Maintenance

Resolved Mar 14 at 10:25am EDT

At this time all servers have been successfully migrated and are now back online. This will conclude the maintenance for Group B.

We thank you for your patience during this move.

If your server does not come on automatically, please visit your control panel via your client portal and boot the server from there.

Thank you.

10 previous updates

Mar 12, 2025
1 maintenance

ASH-5-02 RAM Upgrade

Maintenance

Resolved Mar 12 at 03:20pm EDT

This is now done.

1 previous update

Mar 04, 2025
1 maintenance

ASH-4-02 & ASH-4-03 Relocation

Maintenance

Resolved Mar 04 at 12:10pm EST

This is now completed and all Nodes are back online. If your VPS is not online, boot it from the VPS dashboard.